ERM were engaged to carry out modifications to existing heating system at the above school.

This work involved the following:

  • Draining down complete school.
  • Removal of 23 No. Cast Iron Radiators from Basement to Third Floor.
  • Extend existing flow and return services out to accommodate installation of new pre-insulated plasterboard walling.
  • Installation of 23 No. Vogel and Noot Radiators onto new wall.
  • Refill heating system and test.

This work commenced in June 2016 and was completed August 2016